Project Timeline

Efficient project management often requires precise calculation of workdays, excluding weekends and holidays. In this article, we will demonstrate how to calculate project start and end dates using the WORKDAY and NETWORKDAYS functions in Excel.

Calculate project start and end dates using WORKDAY and NETWORKDAYS

The WORKDAY function calculates the end date after a specified number of workdays, while NETWORKDAYS calculates the number of workdays between two dates. These functions are particularly useful for planning and tracking project timelines.

Example

Below is an example table showing how to calculate project start and end dates using WORKDAY and NETWORKDAYS functions:

TaskStart DateWorkdaysEnd DateEnd DateTotal Workdays
Design2024-07-01102024-07-15=WORKDAY(B2, C2)=NETWORKDAYS(B2, D2)
Development2024-07-16152024-08-05=WORKDAY(B3, C3)=NETWORKDAYS(B3, D3)
Testing2024-08-0652024-08-12=WORKDAY(B4, C4)=NETWORKDAYS(B4, D4)

Exercise

Now it's your turn to calculate project timelines. Use the provided Excel sheet to determine the end dates and total workdays for the tasks listed below:

Solution

To solve the exercise, follow these steps:

  1. Enter the start date in the cell.
  2. Use the WORKDAY function to calculate the end date based on the duration.
  3. Use the NETWORKDAYS function to calculate the total workdays between the start and end dates.

Example Calculation:

  • For the "Analysis" task:
    • Start Date: 2024-09-01
    • Duration: 8 workdays
    • Formula for End Date: =WORKDAY(B2, C2)
    • Result: 2024-09-11
    • Formula for Total Workdays: =NETWORKDAYS(B2, D2)
    • Result: 8